Revised OHS regulations on temporary stairs at construction sites take effect Jan 1
table {
border-collapse: collapse;
}
th, td {
padding: 8px;
border-bottom: 1px solid #b4b3b3;
}
tr:hover {background-color: #e6ecf3;}
Current Rule | New Rule (changes in bold face) |
Stairs must be installed before construction of a building or structure that will be at least 2 storeys when it’s finished | Stairs must be installed before construction of any building or structure regardless of how many storeys it will be when it’s finished |
As construction of a building or structure progresses, permanent or temporary stairs must be installed up to: (a) the uppermost work level; or (b) if stairs would interfere with work on the uppermost work level, no more than 2 storeys or 9 metres below the uppermost work level, whichever is shorter |
As construction of a building or structure progresses, permanent or temporary stairs must be installed from the lowest level, including the basement, up to: (a) the uppermost work level; or (b) if stairs would interfere with work on the uppermost work level, no more than 2 storeys or 9 metres below the uppermost work level, whichever is shorter |
The above installed-up-to requirement doesn’t apply to: (a) a part of a building or structure in which only the structural steel beams or columns are erected; or (b) a structure to which a permanent ladder is attached before the structure is raised into position |
The above installed-up-to requirement doesn’t apply to: (a) a part of a building or structure in which only the structural steel beams or columns are erected; (b) a structure to which a permanent ladder is attached before the structure is raised into position; or (c) a part of a building or structure in which formwork or falsework is erected to a suspended slab |